Expected Project Timeline
2025 Q4
• Sign the PSA with the Tanzanian government.
• Strengthening the core project team.
• Comprehensive review, and compilation of all documents.
• Preliminary meeting with KOGAS.
2026 Q1
• Initiate full-scale discussion with KOGAS and other major Korean/Foreign partners.
• Consortium and Joint Venture(JV) structure negotiations.
• Intensify technical and financial feasibility studies.
• Secure key regulatory permits and advance host government negotiations.
2026 Q2-Q4
• Finalize JV structure, partnership roles, and basic investment commitments.
• Complete Front-End Engineering Design(FEED).
• Launch formal Host Government Agreement(HGA) negotiations.
2027
• Wrap up HGA and major permitting procedures.
• Secure long-term off-take (SPA) agreements.
• Reach Final Investment Decision(FID), finalize main project funding and EPC selection.
• Begin early infrastructure work and order long-lead items.
2028-2029
• Full-scale plant, marine, and sea-bed pipeline construction.
• Continuously monitoring local procurement, workforce training, and community programs.
2030
• Complete main construction.
• Start pre-commissioning and cold testing of all systems.
Early 2031
• Begin commissioning of the LNG plant
• Achieve first production and export of LNG cargo
• Ramp-up to steady-state commercial operations.
Disclaimer
the project timeline presented here is an indicative estimate based on our best current assumption and planning. Actual schedules may be subject to change due to regulatory approvals, financing arrangements, partner selection, and other external factors beyond the company's control. Any material changes to the timeline will be promptly communicated through this website and official disclosure.